Part 9 -
Handling and Placing
The design of concrete is very important to strength and durability, however, attention
should be placed on handling, placing, and curing to ensure uniform quality throughout the
mix. In this section we will discuss the proper handling and placing techniques.
Batching and Mixing
- Batching
-- Batching of aggregates and cement should always be done by weight. Other components,
like water and admixtures, can be batched by volume. Batching by weight allows rapid and
convenient adjustment of mix parameters if desired. Material quantities should be measured
with a high degree of accuracy.
- Batching
Equipment -- Any piece of batching equipment should allow free and unobstructed
flow of materials while minimizing segregation. Machines of this type may be divided into
three categories: (1) manual - used for small jobs or low output requirements; (2)
semiautomatic - batching process is manually started but is automatically terminated; (3)
fully automatic - in this device a single switch activates the entire batching procedure.
All of this devices should be kept clean and as dust free as possible. Avoid free fall of
fine particles, like cement and admixtures to reduce dust and material loss. Weighing
device should be checked often to ensure that the proper amounts of each material is being
batched correctly.
- Handling of
Aggregate -- The main objective in handling aggregate is to prevent segregation
and control moisture of the material. Segregation problems can be minimized by storing
coarse aggregate in coarse, medium, and fine factions. This will allow the proper
gradation of the aggregate. Protection from the weather can prevent wide variation in
moisture content.
- Mixing
-- Proper mixing is essential to produce homogeneous, uniform concrete. Inadequate mixing
will result in concrete with lower strengths and greater batch-to-batch variations.
Excessive mixing will reduce the output of a batching operation and can lead to breakdown
of the aggregate.
- Mixing Times
-- The optimum mixing time depends on several factors; (1) the type of mixer, (2) the
condition of the mixer; (3) the speed of the mixer; (4) the size of the charge; (5) the
nature of the materials. In general, mixing time should be assessed in the field based
upon batch-to-batch variations. Lean, dry, or harsh mixes require longer mixing times.
Concrete made with angular aggregates required more time than do concretes with more
rounded aggregates.
- Charging the
Mixer -- This refers to the pre-blending of materials. Generally, it is desired to
add about 10% of the mixing water before the aggregates are added and continuously added
throughout the charging of the aggregate. The cement should be added after about 10% of
the aggregate has been added. Admixtures should batched separately to avoid any potential
adverse interactions between them.
- Types of
Mixers -- Generally, mixers can be divided into three types; (1) drum mixers - a
series of interior fixed blades which ensure end-to-end mixing of the materials. The
concrete can be removed by dumping the mix or reversing the direction of rotation; (2) pan
mixers - in this type the mixing blades are fixed and the pan rotates; (3) continuous
mixers - the materials are proportioned at one end of a drum, mixed in the drum, and exit
the other end of the drum as concrete.
- Ready-Mixed
Concrete -- By using automated equipment and trained personnel ready-mix
operations can obtain better quality control. This type of operation also eliminates the
need for mass storage of materials on the job site. There are several ways to handle this
type of operation; (1) central-mixed - completely mixed at the batching plant, truck is
used mainly for transportation, mixing in the truck reduces slump loss and prevents
segregation; (2) transit-mixing - concrete is partially or completely mixed in transit;
(3) shrink-mixed - concrete is partially mixed at the plant to reduce the volume and
completed in the truck mixer (4) truck-mixed - completely mixed in the truck after being
charged at the plant.
- Remixing
-- Concrete is often remixed at the job site to ensure proper slump is achieved. If this
is the case, at least half the mixing time should occur during the remixing. Remixed
concrete is likely to set more rapidly than concrete mixed only once.
Transportation
There are many different ways to handle concrete and the choice will depend many
factors. In general, any means of transportation should protect the concrete from weather
and avoid segregation.
Pumping
Concrete pumping technique were developed in the 1930's but remained uncommon until 15
to 20 years ago. Typically, concrete can be pumped more than 1500 feet horizontally and
500 feet vertically. There are three basic types of concrete pumps; (1) piston pumps; (2)
pneumatic pumps; and (3) squeeze pumps. Pipelines are made of rigid or flexible material.
Generally the rigid pipe performs better allowing up to 8 in. diameter section, while
flexible pipe is limited to about 4 in. inner diameter.
- Pumping
Distances -- The distance concrete can be pumped depends on many factors; (1) the
capacity of the pump, (2) the size of the pipeline, (3) obstructions top uniform flow, (4)
velocity of pumping, and (5) the characteristics of the concrete. The concrete is pumped
as a plug lubricated by a thin layer of mortar or grout at the pipe wall. The is achieved
by priming the pump with a mortar or a concrete with the coarse aggregate removed.
- Mix Design
-- If concrete is to pumped it should be designed to be plastic and cohesive with emphasis
on quality control and uniformity of components. Harsh or dry mixes do not pump well. Most
failures in pumping occur because of segregation and high frictional resistance. To avoid
such problems, the maximum aggregate size should be restricted to 33% of the inside pipe
diameter for angular aggregates and 40% for rounded aggregates. Special attention must be
given to the amount of fine aggregate in the mix since the mortar fluid is the pumping
medium in which the coarse aggregate is suspended. Admixtures are available which increase
the viscosity of the mixing water preventing excessive bleeding and reducing frictional
resistance. Concrete of high slump can segregate in the pipeline and cause blockage.
Air-entrained concrete can be pumped if the air content is not too high. The
compressibility of air reduced pumping capacity.
Placement of Concrete
Proper handling of concrete during placement should minimize segregation of coarse
aggregates. Basically, concrete should be placed by a vertical drop, however, the material
should not be allowed to free fall for long distances. Concrete should be allowed to flow
slowly into the forms at a vertical angle. If placement on a slope is desired the concrete
should be constrained to fall vertically by some sort of chute or baffle.
Special Placement
- Slip Forming
-- A method for the continuous placement and consolidation of concrete. In this technique
low slump concrete capable of retaining it shape without formwork shortly after placement
is used for horizontal applications. In vertical application the formwork must remain
until the adequate strength has been gained. A variation of this method is the jump
forming technique. In this method the forms are not moved continuously, but repositioned
of jump to the next lift.
- Preplaced
Aggregate -- In this method, forms are packed with well-graded aggregates and
injected with mortar to fill the voids. This method is used for underwater placement of
when normal placement is very difficult. Since the aggregate is packed more densely than
ordinary concrete, less cement paste is required. The direct contact between aggregate
will affect the elastic and fracture properties of concrete.
- Shotcreteing
of Gunniting -- In this method concrete is applied by spraying it from a nozzle
by means of compressed air. Normally, the material are blended dry and the water is
injected just before entering the nozzle. The concrete can also be sprayed in a wet state.
Generally, fine aggregate and sand are used in shotcreteing operations. The force of the
spray compacts the concrete at the surface resulting in high compressive strengths. Up to
1/2 of the mixture rebounds off the surface and is lost. This results in a richer mixture
than the design mix.
- Tremie
Concrete -- This method is used for pouring concrete underwater or placement in
deep forms. The concrete is placed by gravity through a long vertical pipe with a
funnel-shaped hopper at the end. This method is designed to eliminate trapped air or voids
in the concrete. To obtain the high slump, flowing concrete necessary for this technique a
high percentage of sand, 40 to 50% by weight of total aggregate, is used. The size of the
tremie pipe depends on maximum aggregate size.
- Underwater
Placement -- The tremie method is only one method for underwater placement.
Pumping and preplaced aggregate methods are also used. Special bottom-dump buckets are
also used to place concrete underwater.
Consolidation
After placement, the concrete should be consolidated into the forms and around
reinforcing bars to eliminate trapped air and voids. Most concrete now placed is
consolidated by vibration. The main advantage of this technique over other methods is that
concrete can have as little as 1/3 the slump of concrete consolidated by hand. Lower slump
mixes are also less prone to segregation. Overvibration will bring excessive paste to the
surface, enhances bleeding, and causes loss of entrained air.
- Concrete
Vibrators -- Basically, a vibrator applies periodic shear forces to the concrete
which causes the material to flow. There are generally two types of vibration devices;
internal or immersion vibrators or external vibrators. External vibrators clamp direct to
the formwork requiring strong, rigid forms which remain watertight to withstand the energy
imparted to the system. Internal vibrators are more suited general construction. As the
concrete is caused to flow by the vibration it does not flow uniformly. As the vibration
starts the dense coarse aggregate is forced away form the vibrator head and mortar begins
to flow between the aggregate. The vibrator head must be moved up and down to create a
homogeneous mix. To aid in the removal of trapped air the vibrator head should be rapidly
plunged into the mix and slowly moved up and down. Any trapped air flows away from the
head and to the forms. As the head is pull out the air is forced out along the form sides
ahead of the vibrator. Vibration has a limited sphere of influence. Typically, the
concrete should be vibrated at 18 inch intervals and at each lift. Revibration can produce
better consolidated concrete if done before final set.
- Vacuum
Dewatering -- A method of consolidation of horizontal surfaces which removes
water form the upper 12 inches of the slab, effectively consolidating the material. A
filter prevents the removal of fine particles. The lower w/c ratio improves strength and
durability.
Casting in Lifts
When casting in lifts units between construction joints should be cast in successive
layers. Each layer should be vibrated together by passing the vibrator into the lower
lift. If the lower lift hardens before the nest placement, a cold joint or construction
joint must be used. The lower lift surface is cleaned to create a roughened state so that
a good mechanical bond with the next lift can be made. A layer of mortar helps provide a
good bond and reduced the potential for segregation.
Finishing Concrete
Several techniques have been developed for finishing slabs for floors or pavements.
Good finishing can provide a maintenance free surface and can offset some deficiencies of
a poorly designed mix.
- Screeding
-- Excess concrete is struck off to bring the surface to the desired level and fill any
low spots.
- Floating
-- After the concrete has hardened and bleed water has disappeared, the surface is floated
to a flat blade. This process compacts and removes imperfections from the surface while
forcing cement and water to the surface. Excessive floating will cause a high w/c ratio
and weaken the surface.
- Trowelling
-- After floating, a surface may be steel-troweled to provide a really smooth, dense,
wear-resistant surface.
- Texturing
-- If a skid-resistant surface is desired, the freshly screeded surface can be textured by
scoring the surface with a wire or fiber broom. Excessive paste can be removed with
washing which results in an exposed aggregate finish.
- Hardening
-- This treatment causes the surface to provide additional durability and wear-resistance.
This is the result of a chemical reaction with calcium hydroxide in the paste creating
more C-S-H.
-
This website was originally developed by
Charles Camp for his
CIVL 1101 class.
This
site is maintained by the
Department of Civil
Engineering at the
University of Memphis.
Your
comments and questions are more than welcome.
|